TERRAMESH RETAINING WALL KORCA-ERSEKA-LOT2 PHASE1

年份
2022
地点
KORCA - ALBANIA - Albania
客户
ANK shpk
设计者
A&E Engineering " Sh.p.k.

挑战

The Korca - Erseka Road project is located in the southeast of Albania. The project construction started in March 2021 and finished the first part in January 2022. Currently, the road axis Korca-Erseka has a length of 45 kilometers, while with the completion of the new segment the distance is reduced to 35 kilometers. Its construction will promote the further development of tourism in the southeast of the country by bringing closer two areas with great potential, such as Korca and Erseka. With its completion, the distance between Korca and Erseka is reduced to 20 minutes. Being an unique design with back to back earthed filled structures, the contractor company ANK asked Maccaferri for our support for these project. After runing the profiles in Macstars 4.0 we found out that the geogrid reinforcement lengths weren’t satisfying the stability checks. cks.

解决方案

Firstly we redesigned the solution using Terramesh units with dimensions 3x3x1x1m. To ensure stability, Terramesh System was reinforced with Paralink 300 and Macgrid WG15,11,8 according to the software Macstars2000 calculations. This way we gave them the most cost effective solution. The construction of the wall started in March 2021 and it was finished in January 2022.  In total 4 Terramesh back to back walls were build around 31’500m2 of facade. Wall 1 L=325m ; Max height H=32m Wall 2 L=130m ; Max height H=20m Wall 3 L=50m  ; Max height H=12m Wall 4 L=525m ; Max height H=16m 

下载 成功案例

TERRAMESH RETAINING WALL KORCA-ERSEKA-LOT2 PHASE1

下载
TERRAMESH RETAINING WALL KORCA-ERSEKA-LOT2 PHASE1

我们的相关
产品 成功案例

联系我们

如果您同意公司的隐私政策并已理解其内容,数据控制者将询问您是否同意按照公司隐私政策规定的方式处理您的数据,以便发送有关数据控制者提供的服务/活动的推广性通讯。 *

此外,数据控制者还将询问您是否同意将您的个人数据传输给 Maccaferri 关联公司,以及由此可能产生的欧盟境外数据传输,用于这些关联公司自身的目的,包括推广性目的(发送营销通讯) *