Facebook pixel

Slope Stabilisation and Green Wall Solution at Kuranda Range, Queensland

Home > News > Slope Stabilisation and Green Wall Solution at Kuranda Range, Queensland
13 July 2026

Slope Stabilisation and Green Wall Solution at Kuranda Range, Queensland

Terramesh® Green wall at Kuranda Range, QLD: 21 years of vegetation growth on a World Heritage rainforest reinforced soil structure.

A trial reinforced soil structure built to prove a green-faced retaining system for a major World Heritage rainforest upgrade has spent two decades quietly demonstrating what long-term vegetation integration looks like in practice.

 

In 1999 the Queensland Government began consulting on a major upgrade to the Kuranda Range Road, the key crossing linking Cairns to the Atherton Tablelands and Cape York. The proposed works were substantial: a four-lane, 16-kilometre realignment with 16 bridges, roughly 60,000m² of fill batters up to 25 metres high, delivered over an expected ten-year program.

 

The setting made the project anything but straightforward. The alignment ran through Far North Queensland’s tropical climate and, critically, through World Heritage-listed rainforest under the jurisdiction of the Wet Tropics Management Authority (WTMA). Alongside environmental sensitivities, the project also had to manage frustrated local businesses and the demands of Cape York access tourism throughout a decade-long construction program. Given these constraints, Terramesh® Green was appended to the project’s Environmental Impact Assessment as a preferred technology for the fill batters.

 

Installed Green Terramesh System

Terramesh® Green is a modular reinforced soil system built for exactly this kind of application. Each unit unit consists of a prefabricated single length of double twist steel wire mesh forming a lid, an inclined front face and an extended integral base referred to as the reinforced tail section. The inclined face section is lined with an erosion control blanket and stiffened with a welded mesh panel which provide stability during filling and enhances the establishment of natural or introduced vegetation. With a 120-year design life and the ability to install around 150m² in a single shift, the system offered the Queensland Department of Main Roads (QDMR) a way to combine structural performance with genuine rehabilitation value for the surrounding rainforest.

 

Proving the technology on site

Before committing the technology to such a large program, QDMR’s design team required proof of concept. Maccaferri approved a trial structure and provided product and site support, tendering a design proposal for evaluation. As the project progressed, a new site was selected requiring a larger structure than originally planned, and the Rainforest Cooperative Research Centre (CRC) was brought in to advise on species selection and planting.

The final trial was built: a 5.4-metre-high, 36-metre-long Terramesh® Green wall. Maccaferri’s design suggestion used a layered internal stability configuration incorporating Terramesh® units, green-faced Terramesh sections, and geogrid reinforcement. QDMR prepared the site to accept the structure, and Maccaferri supplied the materials.

 

Maccaferri Proposed Design

 

Building the wall

 

Construction followed a compact program. Site preparation with a 20-tonne excavator took five days, followed by two days of final trim, half a day of irrigation works, and a single day of planting. The crew comprised two labourers, a ganger, foreman and supervisor, supported by a 20-tonne excavator, a 5-tonne roller and a mini front-end loader. Materials included 170 Terramesh® Green units, five rolls of Maccaferri geogrid, two rolls of stripdrain, and one roll of geotextile.

 

Construction moved through clear stages: a non-woven geotextile and drainage layer at the base, gabion mesh units built up and filled in stepped, angled lifts to match the batter profile, vegetative soil placed behind the front face, and the exposed face scarified ahead of hydromulching. Endemic shrubs, ferns, gingers and rainforest tree species selected through the CRC were then planted directly through the facing mesh.

 

Assembling Green Terramesh Units

 

The wall was built at an average rate of roughly 86m³ of fill placed, spread and compacted per day, with the full 5.4m structure completed in 12 days. The stepped, angled face suited the batter profile and made construction straightforward to repeat, requiring minimal labour input. Fully installed cost, including placing and compacting backfill. The finished structure was assessed as aesthetically acceptable, with favourable comments received from stakeholders.

 

Two decades of vegetation growth

 

The real test of a green-faced reinforced soil system is what happens after construction, and the Kuranda trial has now been observed for more than 20 years.

By June 2006, seven months after completion, the face was already carrying dense grass cover and establishing shrub growth. By March 2012, sections of the wall had developed into what site inspectors described as the “greenest” section of the slope, with canopy species visibly integrating into the surrounding rainforest edge.

 

Completed Structure After 7 Months

 

Photographs taken in March 2026. 21 years after installation, show a structure that is now visually indistinguishable from the native rainforest verge beside it. Mesh facing is fully obscured by established shrubs, grasses and trees, with root systems growing directly through and around the original Terramesh® Green units.

 

March 2026 – 21 years after installation

 

A structural solution that became part of the landscape

 

What began in 2005 as a trial to prove a reinforced soil technology for a major road upgrade has, over 21 years, evolved into a self-sustaining section of rainforest edge. The Kuranda Range trial demonstrates that Terramesh® Green can deliver both the structural performance required for large fill batters and the long-term ecological outcomes demanded by sensitive environments such as World Heritage rainforest, a practical example of engineered systems working with nature rather than against it.

 

For more information, contacts us at [email protected].

 

Related Products

TerraMesh
TerraMesh
Maccaferri Terramesh® Family includes different facing options to build a Mechanically Stabilized Earth (MSE) structures and Reinforced Soil SlView
star