TIRANA ELBASAN HIGHWAY

Viti
2013-2019
Vendndodhja
ELBASAN - ELBASAN - Albania
Klienti
COPRI - AKTOR
Projektuesi
AKTOR-MACCAFERRI

Sfida

The Tirana–Elbasan Highway is a four-lane highway in central Albania and part of the A3 motorway opened to traffic on 16 June 2013, and completed in the summer of 2019. It covers the distance between the cities of Tirana and Elbasan in the shortest way possible and its total length is 16 kilometres

The project faced many technical challenges as the topography of the route is such that it will require the construction of tunnels, bridges, embankments. Numerous overpasses, underpasses and viaducts will also need to be built.


The client wanted to reach the design level in the entrance of the tunnel and decided to adopt a mixed RSS solution (wire mesh+PET geogrids) as main type of retaining solution for this project.


Zgjidhja

This project included different types of reinforced soil structures with gabions and mattresses for river protection and Green terramesh & Terramesh system.

The design and solution proposed by Maccaferri were applied in different locations through out the whole project depending on the site and geotechnical conditions.  



Shkarkoni Histori Suksesi

TIRANA ELBASAN HIGHWAY

Shkarko
TIRANA ELBASAN HIGHWAY

Produktet tona për
këtë Histori Suksesi

Lidhuni me ne

Nëse jeni dakord me Politikën e Privatësisë të kompanisë dhe keni kuptuar përmbajtjen e saj, Kontrolluesi i të Dhënave ju pyet nëse jepni pëlqimin për përpunimin e të dhënave në mënyrën e parashikuar nga politika e privatësisë e kompanisë, për dërgimin e komunikimeve promovuese për shërbimet/aktivitetet e ofruara nga Kontrolluesi i të Dhënave. *

Për më tepër, Kontrolluesi i të Dhënave ju pyet nëse jepni pëlqimin për komunikimin e të dhënave tuaja personale te Filialet e Maccaferri, dhe transferimin e mundshëm jashtë BE-së që mund të rezultojë, për qëllimet e tyre, përfshirë ato të natyrës promovuese (dërgimi i komunikimeve të marketingut) *