ÇÖPLER GOLD MINE ROCK FALL PROJECT

Viti
2018-2019
Vendndodhja
ERZİNCAN - DOĞU ANADOLU - Turkey
Klienti
ANAGOLD MADENCİLİK SAN. ve TİC. A.Ş.

Sfida

The Çöpler mine site is an open pit operation located 8 km away from Ilıc District of Erzincan City, approximately 550 km east of Ankara in Middle Anatolia with the capacity to process approximately 20,000 tonnes of oxide ore per day. During the extension of the waste storage area, rockfall from the rocky slopes next to the construction area forced the company to stop the construction temporarily in order to prevent damage on the membranes and to decrease the risk for the construction crew.

Zgjidhja

In accordance with the urgency of the situation, the size of the potentially dangerous rocks on the slope and in line with the technical and economic conditions, Steel Grid HR100 has been installed on the steep slopes running along the waste storage area. The total area of approximately 30,000 m² has been installed in a time period of 4-6 weeks under the cooperation with our professional mountainer crew.

Shkarkoni Histori Suksesi

ÇÖPLER GOLD MINE ROCK FALL PROJECT

Shkarko
ÇÖPLER GOLD MINE ROCK FALL PROJECT

Produktet tona për
këtë Histori Suksesi

Lidhuni me ne

Nëse jeni dakord me Politikën e Privatësisë të kompanisë dhe keni kuptuar përmbajtjen e saj, Kontrolluesi i të Dhënave ju pyet nëse jepni pëlqimin për përpunimin e të dhënave në mënyrën e parashikuar nga politika e privatësisë e kompanisë, për dërgimin e komunikimeve promovuese për shërbimet/aktivitetet e ofruara nga Kontrolluesi i të Dhënave. *

Për më tepër, Kontrolluesi i të Dhënave ju pyet nëse jepni pëlqimin për komunikimin e të dhënave tuaja personale te Filialet e Maccaferri, dhe transferimin e mundshëm jashtë BE-së që mund të rezultojë, për qëllimet e tyre, përfshirë ato të natyrës promovuese (dërgimi i komunikimeve të marketingut) *