Reinforced Soil Walls and Slope Reinforcement
2020
HULU SELANGOR - SELANGOR - Malaysia
Public Works Department Selangor
BRIDGE ABUTMENT AT HULU SELANGOR, MALAYSIA
Problem
As works have to be completed on fast track basis, the client has agreed to adopt our Terramesh System which would be used as a temporary bailey bridge. This is to allow demolition of the old bridge and, subsequently, construction of a new bridge to take place. The time used to construct both sides of the bailey bridge abutment using this Terramesh System was merely 3 weeks.
Solution
Apart from its fast-paced installation and construction, Terramesh was chosen because of considerable savings in the overall cost. The Terramesh boosts a height of 7m for both sides of bailey bridge abutment. This structure was also designed to take loads up to 150 kPa as long trailers transporting Perodua Car ply there regularly.