ÇÖPLER GOLD MINE ROCK FALL PROJECT

Année
2018-2019
Lieu
ERZİNCAN - DOĞU ANADOLU - Turkey
Client
ANAGOLD MADENCİLİK SAN. ve TİC. A.Ş.

Défi

The Çöpler mine site is an open pit operation located 8 km away from Ilıc District of Erzincan City, approximately 550 km east of Ankara in Middle Anatolia with the capacity to process approximately 20,000 tonnes of oxide ore per day. During the extension of the waste storage area, rockfall from the rocky slopes next to the construction area forced the company to stop the construction temporarily in order to prevent damage on the membranes and to decrease the risk for the construction crew.

Solution

In accordance with the urgency of the situation, the size of the potentially dangerous rocks on the slope and in line with the technical and economic conditions, Steel Grid HR100 has been installed on the steep slopes running along the waste storage area. The total area of approximately 30,000 m² has been installed in a time period of 4-6 weeks under the cooperation with our professional mountainer crew.

Télécharger
l' Étude de cas

ÇÖPLER GOLD MINE ROCK FALL PROJECT

Télécharger
ÇÖPLER GOLD MINE ROCK FALL PROJECT

Nos produits pour
cette Étude de cas

Entrez en contact avec nous

Si vous êtes d'accord avec la Politique de confidentialité de l'entreprise et que vous en avez compris le contenu, le Responsable du traitement vous demande si vous consentez au traitement selon les modalités prévues par la politique de confidentialité de l'entreprise, aux fins de l'envoi de communications promotionnelles relatives aux services/activités proposés par le Responsable du traitement. *

En outre, le Responsable du traitement vous demande si vous consentez à la communication de vos données personnelles aux Sociétés Affiliées Maccaferri, ainsi qu'au transfert hors UE qui pourrait en résulter, aux fins propres de ces dernières, y compris à des fins promotionnelles (envoi de communications marketing) *