Desafio

The modernisation works on the Acayucan - La Ventosa road include the widening of the crown from 7m to 12m, as well as the correction of curves and gradients to maintain operating speed. The new layout shifts the axis and zeros lines of the current road, which passes through numerous population centres, including Estación Sarabia at km 174+770, where space to accommodate the over-widths is limited.

Solução

The constructor together with the external supervision and the SICT residence analysed different alternatives for the required retaining works, and the one proposed by Maccaferri with a 4m high gabion gravity wall and internal staggering was chosen. The construction of a trapezoidal section channel was also considered in order to direct the discharges from 2 transversal drainage works towards the nearest natural watercourse.

Descarregue
o Caso de Sucesso

MURO DE CONTENCION CARR. ACAYUCAN - LA VENTOSA

Descarregar
MURO DE CONTENCION CARR. ACAYUCAN - LA VENTOSA

Entre em contacto connosco

Se concorda com a Política de Privacidade da empresa e compreendeu o seu conteúdo, o Responsável pelo tratamento pergunta-lhe se consente o tratamento, na forma prevista na política de privacidade da empresa, para o envio de comunicações promocionais relativas aos serviços/atividades disponibilizados pelo Responsável pelo tratamento. *

Além disso, o Responsável pelo tratamento pergunta-lhe se consente a comunicação dos seus dados pessoais às Afiliadas Maccaferri, e a consequente transferência extra-UE que daí possa resultar, para fins próprios destas últimas, incluindo os de natureza promocional (envio de comunicações de marketing) *