SCHOTEN HOOGMOLENBRUG BRIDGE 54

Type of project
Reinforced Soil Walls and Slope Reinforcement
Year
2021
Location
SCHOTEN - VLAANDEREN - Belgium
Client
Texion Geosynthetics NV

Challenge

With almost 40 million tons of goods transported per year, the Albert Canal is the most important waterway in Flanders. Container transport, in particular, has seen a steep rise over the past decade. As part of the effort to increase the capacity of the Albert Canal, De Vlaamse Waterweg nv is therefore investing in the further expansion of the Albert Canal. The current limitation in clearance height and width under the bridges forms a bottleneck for inland navigation on the Albert Canal. The raising of the bridges to a vertical clearance of 9.10 m will allow barges with four layers of containers to sail safely and smoothly. In addition, Short Sea Shipping will have better opportunities on the Albert Canal. The new Hoogmolen bridge is located on the reservation strip of the A102 and is used as the main connection for freight traffic between both banks, in combination with the Houtlaan. There is an additional bicycle connection and attention is paid to embedding in the landscape. For this purpose, the Hoogmolen bridge 'was moved' 250m towards Antwerp to provide: -A direct link between N120 (Merksemsebaan - Bisschoppenhoflaan) and Metropolitan street -Schoten's traffic safety/livability: keep freight out of the center -High-quality cycle connection between both banks -Landscape connection between both banks - Green Corridor

Solution

The design of the reinforced soil structure has been carried out following the Eurocode 7 in combination with the Belgian Annex. The possibility to modify the units to follow the exact shape of the bridge has been very well appreciated by the contractor FRANKI, that later chose the same system for the next bridges on the Albert Canal, like in Meerhout and Kuringen. In this case, the original plan was to have a slope inclination equal to 75°. to respect this design requirement Maccaferri prosed to use 80° Green Terramesh element installed with some little steps between the units. In correspondence to the bridge abutment, some units were directly connected to the concrete wall as a cladding system.

Download
the Success Story

SCHOTEN HOOGMOLENBRUG BRIDGE 54

Download
SCHOTEN HOOGMOLENBRUG BRIDGE 54

Our products for
this Success Story

Get in touch with us

If you agree with the company's Privacy Policy and understood its content, the Data Controller asks you if you consent to the processing in manner provided in the company's privacy policy for sending promotional communications of the services / activities provided by the Data Controller. *

Furthermore, the Data Controller asks you if you give your consent for the communication of your personal data to the Maccaferri Affiliates, and the consequent extra-EU transfer that may result, for their own purposes, including of a promotional nature (sending marketing communications) *