TERRAMESH® VERDE CARRETERA MATARANI KM. 24

Año
2019
Ubicación
ISLAY - AREQUIPA - Perú
Cliente
OBRAS DE INGENIERÍA S.A.C.
Diseñador
HOB CONSULTORES S.A.

Desafío

At km 24, access ramps were required for the bypass road to the town of Mejía, which would pass through agricultural land with an elevation of more than 12 m. in height. Due to the length and height of the ramp, the use of reinforced concrete was ruled out due to the high cost, and also because it was in the middle of agricultural areas, the use of embankments was not considered, with Terramesh® Verde being the best alternative.

Solución

This road uses engineering solutions with reinforced soil walls, Terramesh® System and Terramesh® Verde, which economised the project by saving on bridges and embankments, reducing the margins of expropriation of agricultural land, allowing for walls more than 10 m high. Furthermore, the solutions have a low environmental impact as they are in contrast with the ecosystem of the area. In this section of the road, the use of soil slopes reinforced with Terramesh® Verde was applied for the execution of the access ramps on the road.

Descarga
el Caso de Éxito

TERRAMESH® VERDE CARRETERA MATARANI KM. 24

Descargar
TERRAMESH® VERDE CARRETERA MATARANI KM. 24

Nuestros productos para
esta Caso de Éxito

Ponte en contacto con nosotros

Si está de acuerdo con la Política de Privacidad de la empresa y ha comprendido su contenido, el Responsable del tratamiento le pregunta si consiente el tratamiento de sus datos, en la forma prevista en la política de privacidad de la empresa, para el envío de comunicaciones promocionales sobre los servicios/actividades ofrecidos por el Responsable del tratamiento. *

Además, el Responsable del tratamiento le pregunta si consiente la comunicación de sus datos personales a las Afiliadas de Maccaferri, y la consiguiente transferencia extracomunitaria que de ello pueda derivarse, para fines propios de estas últimas, incluidos los de carácter promocional (envío de comunicaciones de marketing) *