Desafío

Mundra Special Economic Zone, located in Kutch District of Gujarat, is one of the largest SEZ in India. A ROB was proposed over the railway line that cuts across the connectivity road between Mundra and NH 8A. The approaches of ROB were proposed to be retained by ParaWeb® reinforced soil wall system. However, foundation soil comprising primarily of sandy silt with clay was found to have inadequate load bearing capacity to bear the load of retaining walls. Keeping in mind the high water table and high consolidation settlements, a ground improvement technique was required to improve the bearing capacity of soil, reduce post construction settlement and also facilitate the process of implementation. Thus, considering all these factors, stone column technique with a geosynthetic raft was adopted.

Solución

The stone column technique, also known as vibro-replacement or vibro-displacement, is a ground improvement process where vertical columns of compacted aggregate are formed through the soils to be improved. Primary purpose of soil improvement by stone column technique is to increase the bearing capacity of foundation soil and reduce post construction settlement. Stone column derives its support from lateral resistance provided by the surrounding soil, which is caused by: • bulging of the uncemented stone column under the load. • resistance due to surcharge effect. • bearing support offered by intervening soil. The geosynthetic raft is ParaLink®, which is a monoaxial array of geosynthetic strips having unidirectional strength ranging from 100 to 1350 KN/m. The purpose of providing ParaLink® as basal reinforcement is to ensure proper distribution of the load from the superstructure to the stone columns and reduce differential settlements. Ground Improvement details: The area is recommended to be excavated till the founding level where the stone columns are installed. Stone columns: • South side - entire zone including the reinforced and unreinforced section was improved by stone column technique. • North side - owing to relatively better quality of soil, stone columns were provided only under reinforced soil. ParaLink® was laid throughout the entire zone.

Descarga
el Caso de Éxito

ROB FOR CONNECTIVITY BETWEEN MUNDRA AND NH 8A

Descargar
ROB FOR CONNECTIVITY BETWEEN MUNDRA AND NH 8A

Nuestros productos para
esta Caso de Éxito

Ponte en contacto con nosotros

Si está de acuerdo con la Política de Privacidad de la empresa y ha comprendido su contenido, el Responsable del tratamiento le pregunta si consiente el tratamiento de sus datos, en la forma prevista en la política de privacidad de la empresa, para el envío de comunicaciones promocionales sobre los servicios/actividades ofrecidos por el Responsable del tratamiento. *

Además, el Responsable del tratamiento le pregunta si consiente la comunicación de sus datos personales a las Afiliadas de Maccaferri, y la consiguiente transferencia extracomunitaria que de ello pueda derivarse, para fines propios de estas últimas, incluidos los de carácter promocional (envío de comunicaciones de marketing) *