Casos de éxito

Casos de éxito

44 YEAR OLD GABION STRUCTURE
44 YEAR OLD GABION STRUCTURE
As the cliff was above the normal high tide level, it was  considered sufficient to construct a stepped retaining wall   from massVista
star
50 YEAR OLD GABION STRUCTURE – RIVER HUMBER
50 YEAR OLD GABION STRUCTURE – RIVER HUMBER
A ‘half-tide’ gabion wall, 2m high on an 18m wide gabion  apron (0.5m thick). The volume of protection was   approximately 13,Vista
star
A2 / A282 JUNCTION IMPROVEMENTS
A2 / A282 JUNCTION IMPROVEMENTS
The project team needed a solution that steepened the slope, thereby reducing the land take and saving the hedgerow. The main Contractor on the projecVista
star
AEROPORTO PLÁCIDO DE CASTRO
AEROPORTO PLÁCIDO DE CASTRO
Debido a esto fue necesario la adopción de un geosintético tipo geomembrana para impermeabilización de los laterales de la pista y también de un gVista
star
AINLEY INDUSTRIAL ESTATE DEVELOPMENT
AINLEY INDUSTRIAL ESTATE DEVELOPMENT
Maccaferri provided support to the project team and  proposed the MacWall Landmark segmental reinforced soil   wall system. MVista
star
ARTESANO GALLERIA
ARTESANO GALLERIA
The retaining walls were designed using a gravity gabion retaining system. The architectural boundary walls were defined with a maximum thickness of 5Vista
star
ATI PORT EXPANSION
ATI PORT EXPANSION
In order to address the challenge of improving the port expansion grounds at the Manila South Harbor, Asian Terminals Inc. (ATI) is implementing a cosVista
star
AZUDES SITIO RAMSAR RÍO DESAGUADERO
AZUDES SITIO RAMSAR RÍO DESAGUADERO
To date, two of the six planned weirs have been constructed. For the construction of the curtain, approach works and the dissipation basin, gabion boxVista
star
BAHÍA DE PORTMAN
BAHÍA DE PORTMAN
El Ministerio de Agricultura, Alimentación y Medio Ambiente adjudicó las labores de regeneración a la UTE Ciomar Marco. La solución adoptada Vista
star
BARRAGEM CAMPEIRA – CRISTALÂNDIA
BARRAGEM CAMPEIRA – CRISTALÂNDIA
After complex hydrological studies, the dam was resized. The width of the spillway was increased to 125 metres and it was lined with PoliMac® gabionsVista
star
BARRERA DINÁMICA RB 1500 CANTERA BITORIKA
BARRERA DINÁMICA RB 1500 CANTERA BITORIKA
Para dar solución al diagnóstico descrito, se ha instalado una barrera dinámica RB 1500, H=4 metros, con una longitud L=60 metros y anclajes de sueVista
star
BELFAST HARBOUR
BELFAST HARBOUR
The works included dregging of the new berth and  approaches. This involved the disposal of 500,000m3 of   material to sea with trVista
star
BODEGA ARABARTE
BODEGA ARABARTE
Para poder integrar las diferentes fases y partes de la construcción, los técnicos decidieron utilizar un entorno BIM y para ello Maccaferri puso a Vista
star
BONHILL, STIRLING ROAD
BONHILL, STIRLING ROAD
Maccaferri was approached by Barratt Homes to come up  with a suitable solution for the posed site problems. It was   agreed that Vista
star
BORDERS RAIL
BORDERS RAIL
Maccaferri's gabions were used to support widened cuttings  extensively along the 35-mile route which connects   Edinburgh to Vista
star
BOSCASTLE FLOOD DEFENCES
BOSCASTLE FLOOD DEFENCES
To achieve this solution, Halcrow specified a combination of Reno Mattresses and MacMat-R from Maccaferri. Over 7000 sq metres of Maccaferri wire meshVista
star
BROOMLANDS PRIMARY SCHOOL
BROOMLANDS PRIMARY SCHOOL
Once the overall design had been agreed, Maccaferri was engaged to design, supply and install 8 free standing gabion walls which totalled 78.8m in lenVista
star
CARRETERA MA-2100, ENTRE ALARÓ Y ORIENT
CARRETERA MA-2100, ENTRE ALARÓ Y ORIENT
Para dar solución a las inestabilidades generadas se han utilizado diferentes soluciones: En el P.K. 12, ante la presencia de grandes bloques de conVista
star
COBHAM SERVICES HGV PARKING AREA EXPANSION
COBHAM SERVICES HGV PARKING AREA EXPANSION
The proposal was to increase the HVG parking numbers by  79 new spaces, to the west of the petrol filling station. The   proposal Vista
star
COLLEY LANE SOUTHERN ACCESS ROAD
COLLEY LANE SOUTHERN ACCESS ROAD
The ParaLink LTPs will transfer loads of the mechanically  stabilised earth walls into the pile foundations beneath. The maximum heightVista
star
DANFOSS FACTORY
DANFOSS FACTORY
Maccaferri were approached by Quattro Consult Limited in  July 2021 to propose a suitable high strength geogrid for use   as a basVista
star
DEADMAN WASH, TSMC CHANNEL INFRASTRUCTURE
DEADMAN WASH, TSMC CHANNEL INFRASTRUCTURE
Maccaferri worked with Wood Patel Engineering to design a hydraulic solution for the microprocessor manufacturer TSMC. To reduce the soil erosion alonVista
star
DEBRIS FLOW PROTECTION LERINI STREAM
DEBRIS FLOW PROTECTION LERINI STREAM
After a fierce challenge against the competitor, Maccaferri Balkans won this project thanks to a mix of high performing technical solutions, cost effeVista
star
DISCARICA DI BELLOLAMPO V VASCA
DISCARICA DI BELLOLAMPO V VASCA
La realizzazione della vasca prevede l'impiego di una membrana in HDPE, di un gesontetico bentonitico e di un gecomposito drenante per la captazioVista
star
Drainage of structures
Drainage of structures
The adopted solution was the construction of draining trenches using the MacDrain® TD geocomposite as lateral base drains. These drains are designed Vista
star
EROSION CONTROL AGAINST MAMMAL BURROWING
EROSION CONTROL AGAINST MAMMAL BURROWING
Maccaferri was approached by contractors Crown Services Ltd and asked for advise on a suitable steel wire mesh system that could provide the required Vista
star
ESTABILIZACIÓN DE TALUD EN MUTRIKU
ESTABILIZACIÓN DE TALUD EN MUTRIKU
La solución adoptada consistió en la instalación de un sistema de contención flexible mediante Steelgrid, una cuadrícula de bulones y cables horiVista
star
ESTABILIZACIÓN DE TALUDES EN EL PUERTO EXTERIOR DE A CORUÑA
ESTABILIZACIÓN DE TALUDES EN EL PUERTO EXTERIOR DE A CORUÑA
A fin de proteger las instalaciones contra los desprendimientos, se propuso y diseñó una solución mixta con un sistema de contención flexible en eVista
star
ESTABILIZACIÓN TALUDES PUERTO DE ZIERBENA
ESTABILIZACIÓN TALUDES PUERTO DE ZIERBENA
Para asegurar la zona, se diseñó e instaló un sistema de contención flexible de alta rigidez, para limitar al máximo la deformación del terreno,Vista
star
EXPANSION PROJECT “FUSTARET”
EXPANSION PROJECT “FUSTARET”
In this context, a project for the adequacy of the “Fustaret” saline deposit in Súria (Barcelona) has been drafted, where the remnants of potash Vista
star
EXPO HOUSE en DOHA EXPO 2023
EXPO HOUSE en DOHA EXPO 2023
Maccaferri fue seleccionado como proveedor de tecnología para el SISTEMA DE CUBIERTA VERDE (GREEN COVER SYSTEM), debido a la gran variedad de productVista
star
EXTENSION OF THE CHANTERAINES PARK
EXTENSION OF THE CHANTERAINES PARK
The Conseil Général 92 chose double-twist gabion cages because they allow the filling materials to show through easily. The infill stone chosen comeVista
star
FINALIZACIÓN CUARTO CINTURÓN B-40, ENTRE OLESA Y VILADECAVALLS
FINALIZACIÓN CUARTO CINTURÓN B-40, ENTRE OLESA Y VILADECAVALLS
Para poder dar solución a la erosión que provoca la inestabilidad superficial de los taludes y permita una revegetación de éstos, se ha optado porVista
star
FOYLE COLLEGE AND EBRINGTON PRIMARY SCHOOL AND NURSEY
FOYLE COLLEGE AND EBRINGTON PRIMARY SCHOOL AND NURSEY
Maccaferri proposed the use of the MacWall Vertica 4°  Segmental Block Retaining Wall System. The 4° batter of   this system creVista
star
FV17 LIAFJELLET-OLVIKVATNET
FV17 LIAFJELLET-OLVIKVATNET
Maccaferri, in cooperation with its local partner PRETEC AS, proposed an optimized solution to the contractor and the investor, aimed at enhancing theVista
star
Gabion Defense – Cajuca East Corridor
Gabion Defense – Cajuca East Corridor
The Provincial Municipality of Nazca was in charge of the technical file through its technical study department. The hydraulic approach they determineVista
star
GAVIONES DE CERRAMIENTO, BOADILLA DEL MONTE
GAVIONES DE CERRAMIENTO, BOADILLA DEL MONTE
Desde el principio, una solución de gaviones de malla soldada GAVIARQ parecía la solución más adecuada para cumplir con los requisitos de la propiVista
star
HASANKEYF ARCHEOPARK PROJECT
HASANKEYF ARCHEOPARK PROJECT
The retaining walls, which will reach a height of 27 meters within the scope of the Hasankeyf archeopark project, has been designed with Terramesh SysVista
star
HELBOR BROOKLIN
HELBOR BROOKLIN
The solution for this project involved the demolition of the existing retaining wall and the installation of a vertical drainage system using the MacdVista
star
HELLOMAC – Ponza – Cala Fonte
HELLOMAC – Ponza – Cala Fonte
Maccaferri has always pursued innovation and has already taken part in this digital transformation developing a new alert system: HELLOMAC. Thanks to Vista
star
HUHUGAM HERITAGE CENTER
HUHUGAM HERITAGE CENTER
The aesthetics of gabions were desirable, yet a traditional gabion retaining structure would be very expensive. Therefore Maccaferri suggested the useVista
star
IPO DAM SILT CURTAINS
IPO DAM SILT CURTAINS
To address the degradation of the Ipo Dam and mitigate the adverse effects of soil erosion and water contamination, various long-term solutions are beVista
star
KILDARE ROUTE: IRELANDS TRANSPORT 21 SCHEME
KILDARE ROUTE: IRELANDS TRANSPORT 21 SCHEME
Byrne Looby and Partners were engaged by main contractor Siac Ltd, to value engineer the originally designed proposals as detailed on the project drawVista
star
LANPING LEAD-ZINC MINING SANCHONGSHAN DUMP RETAINING WALL PROJECT
LANPING LEAD-ZINC MINING SANCHONGSHAN DUMP RETAINING WALL PROJECT
According to the geological conditions and engineering requirements of the project, the owner and the design unit comprehensively consider the economyVista
star
LICEO LAS LAGUNAS
LICEO LAS LAGUNAS
Se recomendó realizar un muro Terramesh® System PoliMac™ en todo el perimetro trasero, con altura máxima de 9.0m, para evitar problemas futuros. Vista
star
LINCOLNSHIRE EFW
LINCOLNSHIRE EFW
Consulting engineers, Arup, devised a two stage system of  ground level wet and dry holding lagoons. These were   impermeably lineVista
star
LISTENING MIRRORS HISTORIC SITE
LISTENING MIRRORS HISTORIC SITE
In the first phase of the project the peninsula housing the Mirrors was cut off to create an island linked to the mainland by a swing footbridge, and Vista
star
LÖTZGALERIE
LÖTZGALERIE
The client chose the most economical system. The Maccaferri RB 3000 safety net with an energy of 3000 kJ and a height of 5 m. It was a great challengeVista
star
Lower Campbell Repair
Lower Campbell Repair
The erosion control solution consisted of a six to nine-foot-tall, stair-stepped, gabion wall, with a concrete floor base. MaxTex® H 60.1 iVista
star
LUOYANG FOUR RIVER TONGZHI PROJECT
LUOYANG FOUR RIVER TONGZHI PROJECT
Maccaferri Gabion + Renomesh solutions improve the overall defense capability of protecting the river bank. Overall consideration of the relationshipVista
star
M606 MOTORWAY / M62 JUNCTION
M606 MOTORWAY / M62 JUNCTION
Maccaferri’s double twist woven gabions have been used to  create an approximately 450m, the combined length of road[1]side retaining wallVista
star
MacSport AC Monza
MacSport AC Monza
Per il rifacimento del campo di allenamento, sono state coinvolte diverse aziende specializzate nel settore delle infrastrutture sportive, tra cui ItaVista
star
MALLATAS DE PASTOR EN EL PARQUE NACIONAL DE ORDESA Y MONTE PERDIDO
MALLATAS DE PASTOR EN EL PARQUE NACIONAL DE ORDESA Y MONTE PERDIDO
Con el objetivo de reproducir al máximo la arquitectura original de las mallatas de pastor y obtener una integración paisajística acorde a la zona,Vista
star
Marginal Protection for the Tonameca River
Marginal Protection for the Tonameca River
Emergency actions such as dredging and the establishment of temporary embankments were implemented. Subsequently, hydrological and topographic studiesVista
star
Mass Gravity Retaining Walls
Mass Gravity Retaining Walls
According to the premises outlined in the Environmental Recovery Plan (PRAD) provided by the client, the best solution among the available options in Vista
star
MEJORA DEL TERRENO PARA LA PLATAFORMA LOGÍSTICA DE LEIXÕES
MEJORA DEL TERRENO PARA LA PLATAFORMA LOGÍSTICA DE LEIXÕES
La estrategia para abordar el desafío en el Polo 1 de la plataforma logística fue la implementación del geosintéticos para incrementar la capacidaVista
star
MICOROSA ENVIRONMENTAL REMEDIATION PROJECT
MICOROSA ENVIRONMENTAL REMEDIATION PROJECT
The comprehensive solution involved Maccaferri's expertise and a strategic selection of materials to optimize the environmental remediation procesVista
star
MURO DE CONTENÇÃO E ESCADA HIDRÁULICA EM GABIÕES
MURO DE CONTENÇÃO E ESCADA HIDRÁULICA EM GABIÕES
The technical studies carried out indicated that the best solution to the problem presented, among others found on the market, would be two gabion retVista
star
MURO DE CONTENCION CARR. ACAYUCAN – LA VENTOSA
MURO DE CONTENCION CARR. ACAYUCAN – LA VENTOSA
The constructor together with the external supervision and the SICT residence analysed different alternatives for the required retaining works, and thVista
star
MURO GAVIONES SEASCAPE RESORT – FINESTRAT
MURO GAVIONES SEASCAPE RESORT – FINESTRAT
La utilización de los gaviones de malla de triple torsión se pudo adaptar perfectamente a la forma requerida. Para el relleno de los gaviones se decVista
star
NEW ASDA STORE
NEW ASDA STORE
The chosen solution was the MacWall Diamond dry build a segmental block retaining wall system due to its rapid speed of construction, flexibility and Vista
star
NEWHURST ENERGY FROM WASTE FACILITY
NEWHURST ENERGY FROM WASTE FACILITY
Maccaferri proposed the use of its Macline GCL W20 to  impermeably line the attenuation pond and this was   accepted by client HitVista
star
NORTH WALES COASTROAD (A55)
NORTH WALES COASTROAD (A55)
Where the alluvial clay was at its shallowest, after having  removed the refuse, a separator geotextile was placed to   provide a Vista
star
OBRA DE EMERGENCIA EN LA A-317 EN VÉLEZ-BLANCO
OBRA DE EMERGENCIA EN LA A-317 EN VÉLEZ-BLANCO
Para solucionar estos problemas, se realizó una obra de emergencia que fue adjudicada a la empresa Servicios Técnicos Napal, siendo los trabajos ejeVista
star
Ocean Farm 1 – Supply of KikkoNet Net and Net Structure
Ocean Farm 1 – Supply of KikkoNet Net and Net Structure
As a supplier of the new net pen in this project, Maccaferri is in charge of supplying the KikkoNet containment net and its built-in structural reinfoVista
star
OCEANS UMHLANGA MALL
OCEANS UMHLANGA MALL
After evaluating the geotechnical parameters, loading  constraints and required structure geometry, Maccaferri   provided a designVista
star
PARADOR DE NERJA
PARADOR DE NERJA
Para la estabilización superficial de la parte superior del talud, donde se han generado los voladizos, se ha colocado un Sistema Estructural FlexiblVista
star
PARAMESH WALL FOR BAJO – MALAWATAR ROAD SEGMENT
PARAMESH WALL FOR BAJO – MALAWATAR ROAD SEGMENT
The Retaining Wall Structure for Bajo – Malawatar Road Segment is constructed using Paramesh System with a height of 8.5m, consisting of a TerrameshVista
star
PARTICULAR EN BENAHAVÍS
PARTICULAR EN BENAHAVÍS
La solución con gaviones en malla electrosoldada GAVIARQ ha permitido, simultáneamente, obtener pequeños muros de contención con alturas entre 1 yVista
star
PASSAGEM INFERIOR DA RODOVIA BR-101 EM ESCADA
PASSAGEM INFERIOR DA RODOVIA BR-101 EM ESCADA
A containment and verticalization project for the meeting embankment was implemented using the reinforced soil system with the Terramesh System wall. Vista
star
PEACE BRIDGE
PEACE BRIDGE
A 40m long,8m high Green Terramesh® reinforced soil abutment wall to surround and support the high-level bridge bank seat and integrate seamlessly wiVista
star
PRESA FRANCISCO ABELLÁN
PRESA FRANCISCO ABELLÁN
Para proteger a los usuarios y personal de mantenimiento de los posibles desprendimientos, se ha optado por una solución específica para cada situacVista
star
PRESTONS ROAD FLYOVER
PRESTONS ROAD FLYOVER
The avoidance of surcharge on the tunnel and the potential  for differential movement were resolved by supporting the   approach rVista
star
PROTEÇÃO COSTEIRA COM GABIÕES
PROTEÇÃO COSTEIRA COM GABIÕES
To protect and control erosion, PoliMac™ box-type gabion containment was used, together with a PoliMac™ Reno® mattress, used at the pipe outlets,Vista
star
PROTECCIÓN CONTRA CAÍDA DE ROCAS EN ALHABIA
PROTECCIÓN CONTRA CAÍDA DE ROCAS EN ALHABIA
Para garantizar la seguridad vial de la carretera, se realizó una obra de emergencia que fue adjudicada a la empresa Seanto. Dicha obra consta dVista
star
PROTECCIÓN CONTRA DESPRENDIMIENTOS C-13 FONT DE LES BAGASSES
PROTECCIÓN CONTRA DESPRENDIMIENTOS C-13 FONT DE LES BAGASSES
La solución adoptada, además del desbroce y saneo del talud para retirar bloques inestables, incluía la instalación de una serie de barreras dináVista
star
PROTECCIÓN DEL YACIMENTO ARQUEOLÓGICO DE “LES COVES DEL FEM “
PROTECCIÓN DEL YACIMENTO ARQUEOLÓGICO DE “LES COVES DEL FEM “
Se ha optado por la flexibilidad de los gaviones en malla de doble torsión, con marca CE acorde a ETA-15/0219, que ha permitido adaptar la intervenciVista
star
PROYECTO DE AMPLIACIÓN FUSTARET
PROYECTO DE AMPLIACIÓN FUSTARET
En este contexto se ha redactado un proyecto para la adecuación del depósito salino del Fustaret en Súria (Barcelona), emplazamiento en el cual se Vista
star
RAILWAY EMBANKMENT BURROWING PREVENTION
RAILWAY EMBANKMENT BURROWING PREVENTION
Maccaferri’s Anti-Burrowing Mesh has been proven to be a  strong rodent deterrent. Unlike any plastic grids or thin   rabbit netVista
star
REDROW HOMES DEVELOPMENT
REDROW HOMES DEVELOPMENT
The excavated chalk was originally scheduled for landscaping and offsite disposal. However, contractor GDL, their designers GES and Maccaferri determiVista
star
Rehabilitation due to Undermining in Villalobos
Rehabilitation due to Undermining in Villalobos
An environmentally sustainable engineering solution will be implemented. Technologies such as Terramesh System and Macgrid WG will be used to stabilizVista
star
Reinforced Soil Retaining Structure and Slope Reinforcement
Reinforced Soil Retaining Structure and Slope Reinforcement
The client required a solution that met technical, architectural, and environmental requirements, incorporating a green face to transform the retaininVista
star
Reinforced Soil Walls and Slope Reinforcement in HUARAZ – ANCASH – Perú
Reinforced Soil Walls and Slope Reinforcement in HUARAZ – ANCASH – Perú
The major challenge was to propose a reinforced soil wall with a considerable height of 19 meters using the technical-economic competitiveness of the Vista
star
REPAIR AND IMPROVEMENT OF OUELLETTE DRAIN WEST OUTLET
REPAIR AND IMPROVEMENT OF OUELLETTE DRAIN WEST OUTLET
RC Spencer Associates Inc., a reputable engineering firm in  the Windsor area, was tasked by the Town of Amherstburg   to devise aVista
star
RESTAURACIÓN – AUTÓDROMO INTERNACIONAL DE GOIÂNI
RESTAURACIÓN – AUTÓDROMO INTERNACIONAL DE GOIÂNI
Pensando en ello, AGETOP, la agencia estatal responsable de la administración del autódromo, decidió utilizar geomallas para el refuerzo del asfaltVista
star
RESTORATION OF THE ROAD LINK RR 128 AIN OCTOR – KORBOUS
RESTORATION OF THE ROAD LINK RR 128 AIN OCTOR – KORBOUS
The acrobatic works company, Hydrokarst, based in France, solicited Maccaferri to propose solutions for protection against rockfalls. Several types ofVista
star
RETAINING WALL SUPPORTING A630
RETAINING WALL SUPPORTING A630
A PVC-coated welded mesh mass gravity gabion wall was  originally proposed within the design. However, the PVC   coating on weldedVista
star
RETENTION WORKS FOR YADAGIRI GUTTA TEMPLE AREA
RETENTION WORKS FOR YADAGIRI GUTTA TEMPLE AREA
The site of the presidential suite building area is on hilly terrain and the foundation strata is completely rock. The height of the retention is varyVista
star
Road stabilization in Totonicanapá
Road stabilization in Totonicanapá
The use of mono-oriented MacGrid WG geogrids integrated into the Terramesh system offers a superior technical solution for the containment project in Vista
star
ROCKFALL MITIGATION WORKS- RAILWAY LINE-NEAR CH 14 – ANPARA
ROCKFALL MITIGATION WORKS- RAILWAY LINE-NEAR CH 14 – ANPARA
Based on engineering investigations, various site observations and previous history of rockfall events, the critical stretches have been identified. RVista
star
ROCKFALL PROTECTION AT SIMPANG PULAI, PERAK, MALAYSIA
ROCKFALL PROTECTION AT SIMPANG PULAI, PERAK, MALAYSIA
Based on the rockfall trajectory analysis, the design energy level required is 2000 kJ. Flexible barrier with post height of 4m in installed over 500mVista
star
SADAWARNA DAM PARAMESH WALL
SADAWARNA DAM PARAMESH WALL
The Retaining Wall Structure for Stilling Basin in Sadawarna Dam is constructed using Paramesh System with a height of 5m, consisting of the TerrameshVista
star
SAFETY WORKS ON THE RD 900 IN THE ROCHAILL SECTOR
SAFETY WORKS ON THE RD 900 IN THE ROCHAILL SECTOR
As part of the MBC project in the Alpes de Haute Provence department, EPC France called on France Maccaferri to provide a wide range of solutions for Vista
star
SEATION TRAMWAY
SEATION TRAMWAY
The site is situated above an area of soft soil that required  substantial ground improvement.The new platform area   adjacent to Vista
star
Second Stage MME at Puerto Escondido Airport
Second Stage MME at Puerto Escondido Airport
To strengthen the embankment, a longitudinal containment structure was designed and built, combining gabion walls and the Terramesh System along with Vista
star
SLOPE PROTECTION MEASURES- RAILWAY LINE- NEAR CH 13 – ANPARA
SLOPE PROTECTION MEASURES- RAILWAY LINE- NEAR CH 13 – ANPARA
Based on engineering investigations, various site observations and previous history of rockfall events, the critical stretches have been identified. VVista
star
SLOPE STABILIZATION AND PROTECTION AT ULU SLIM RIVER, PERAK
After careful considerations, Jabatan Kerja Raya (JKR) Batang Padang adopted Maccaferri Gabions Retaining Wall to solve this problem and increase safeVista
star
Small green lung in the Metelliana Valley
Small green lung in the Metelliana Valley
Maccaferri’s solution to the environmental challenges posed by the abandoned landfill in Cava de’ Tirreni involved the application of advanced geoVista
star
SNCF LINE 930 000 FROM MARSEILLE TO VINTIMILLE
SNCF LINE 930 000 FROM MARSEILLE TO VINTIMILLE
The work involved installing 3 lines of protective screens on the rock faces located on the slope and in the access trench to the Cap Martin tunnel, fVista
star
SOSTENIMIENTO ROCALLA EN VÍCAR, ALMERÍA
SOSTENIMIENTO ROCALLA EN VÍCAR, ALMERÍA
Para solucionar este problema, se realizó el siguiente sostenimiento:- Red de cable LEA 300-8 de 130 kN/m de resistencia a la tracción y 204 kN de rVista
star
St Andrews Royal & Ancient Golf Club
St Andrews Royal & Ancient Golf Club
The approved scheme was designed by HR Wallingford, to include both ‘hard’ and ‘soft’ engineering solutions and the contract was supervised byVista
star
SUNSET CLIFF
SUNSET CLIFF
La solución adoptada para los muros del “Sunset Cliff” está formada por dos tipos de sistemas: Muros de gravedad mediante gaviones en el caso deVista
star
TERRAMESH RD PATRIMONIAL
TERRAMESH RD PATRIMONIAL
The slope, characterized by its steep incline, created a challenging situation that required the implementation of containment measures to ensure the Vista
star
TERRAMESH® VERDE CARRETERA MATARANI KM. 24
TERRAMESH® VERDE CARRETERA MATARANI KM. 24
This road uses engineering solutions with reinforced soil walls, Terramesh® System and Terramesh® Verde, which economised the project by saving on bVista
star
TERZO VALICO DEI GIOVI – GENOVA JUNCTION
TERZO VALICO DEI GIOVI – GENOVA JUNCTION
Maccaferri proposed an innovative approach involving Automated Tunnel Ribs HEB 300 complete with automated hinges and automated links (covering a lengVista
star
The Ash Yard of the Thermal Power Plant
The Ash Yard of the Thermal Power Plant
The creation of cells was carried out, protected with geosynthetics both at their base and in the closure, with three levels of impermeable protectionVista
star
THE GRAND BOHEMIAN HOTEL
THE GRAND BOHEMIAN HOTEL
Initially, the project specifications called for S8 Aluminum anchors to be driven to a depth of 16'. However, during the installation, numerous prVista
star
THE NEW ROUTE DU LITTORAL
THE NEW ROUTE DU LITTORAL
The solution defined by the project management for the landward embankments was a geosynthetic stiffened embankment with a double-twist gabion facing.Vista
star
THREE CITIES TRAIL
THREE CITIES TRAIL
The civil engineers at Halff successfully designed and  implemented a tie-back reinforced gabion retaining wall to   act as the slVista
star
TK 2018 – 006 – MRV
TK 2018 – 006 – MRV
The solution adopted for this construction case involves a rectangular channel with cross-sectional heights varying between 2 and 4 meters. Gabion BoxVista
star
URBANIZACIÓN SAN SEBASTIAN DE LOS REYES
URBANIZACIÓN SAN SEBASTIAN DE LOS REYES
Para elaborar la propuesta técnica, debido a que la geometría del muro es variable a lo largo de todo el trazado, A. Bianchini Ingeniero decidió deVista
star
VOID SPANNING IN HOUSING DEVELOPMENT
VOID SPANNING IN HOUSING DEVELOPMENT
The Developer’s Engineer approached Maccaferri to providedesign and supply of a high-strength geogrid solution. The proposed site topography was comVista
star
WALTHAM HIGH SCHOOL
WALTHAM HIGH SCHOOL
Based on the rock wall’s height, geotechnical characteristics and the proximity of it to the school, a pinned drapery solution was the recommended mVista
star

¿No encontraste lo que estabas buscando?

Filter by:
Búsqueda Avanzada












Conoce a nuestros expertos

Representamos un socio ganador para el complejo mundo de las construcciones civiles e industriales. Gracias a una amplia gama, nuestros productos son la respuesta a las diversas demandas técnicas del sector: desde drenaje y protección hasta el agua y la impermeabilización de estructuras y revestimientos, pasando por el ahorro energético y la comodidad en la vivienda, desde el control de vapor hasta los problemas relacionados.