RINGFIETSPAD ANTWERP

Ano
2019
Localização
ANTWERP - ANTWERP - Belgium
Cliente
Texion Geosythetics N.V.
Projetista
Tractebel Engineering N.V.

Desafio

This project has implied reinforced soil wall design, material supply and installation for a high-speed bike lane between the neighborhood of Deurne and Borgerhout in the city of Antwerp (Belgium). The main contractor was the Colas Group. Tractebel Engineering N.V. made the whole design with several different inclinations of the RSS to give a more natural and pleasant view. The walls were built along a very trafficked highway and they were aimed to act as a sound barrier for the houses in the suburban neighborhood as well. 

Solução

Mainly, four different types of facing inclinations have been used for this project: 27°, 34°, 45° and 60° The main product used is Terramesh Green Light that was produced specifically to meet the design requirements and slope inclinations. The project included also welded gabions walls and RSS built using EPS blocks to reduce the weight of the walls since the poor bearing capacity of the soil in situ. The construction took place between May 2019 and November 2019. In May 2020 the slopes were already completely vegetated.

Descarregue
o Caso de Sucesso

RINGFIETSPAD ANTWERP

Descarregar
RINGFIETSPAD ANTWERP

Os nossos produtos para
esta Caso de Sucesso

Entre em contacto connosco

Se concorda com a Política de Privacidade da empresa e compreendeu o seu conteúdo, o Responsável pelo tratamento pergunta-lhe se consente o tratamento, na forma prevista na política de privacidade da empresa, para o envio de comunicações promocionais relativas aos serviços/atividades disponibilizados pelo Responsável pelo tratamento. *

Além disso, o Responsável pelo tratamento pergunta-lhe se consente a comunicação dos seus dados pessoais às Afiliadas Maccaferri, e a consequente transferência extra-UE que daí possa resultar, para fins próprios destas últimas, incluindo os de natureza promocional (envio de comunicações de marketing) *