Challenge

A landslide occurred in August 2020 near the Thejaswini Building, below the existing roadway and in front of the CDAC Building within the Technopark Phase I campus, Thiruvananthapuram, Kerala. The affected slope has an average height of approximately 25 m. Site investigations indicated that the failed slope predominantly comprised lateritic soil interbedded with rock layers. The lateritic soil is relatively soft and can be easily cut when wet, although it hardens upon drying and with time. Its plasticity decreases with depth as it transitions towards the parent rock, while the presence of iron oxides contributes to its relatively high specific gravity.

The landslide was primarily triggered by a sudden increase in pore water pressure during heavy rainfall, which significantly reduced the shear strength of the lateritic soil. The lateritic soil layers sandwiched between the rock strata experienced a loss of cohesion upon saturation, resulting in the combined movement of both the soil and overlying rock mass. The considerable slope height, together with the weakened soil conditions and groundwater effects, posed a significant geotechnical challenge requiring a robust and long-term slope retention solution.

Solution

Based on the slope retention requirements, a Green Terramesh reinforced soil wall was implemented as the retaining solution. The system was designed to withstand the anticipated static and seismic loading conditions while ensuring the long-term stability of the slope. The reinforced soil structure was designed to accommodate differential settlements and adapt to the varying ground conditions, making it well suited to the lateritic soil profile.

MacFlex and MacGanics were adopted as the hydroseeding solution to provide erosion control and establish a vegetative finish over the Green Terramesh fascia and reinforced slope. The system is environmentally sustainable and blends seamlessly with the surrounding landscape.

The solution also offered enhanced drainage performance, faster construction compared to conventional rigid retaining structures, and a durable, long-term stabilization system. The maximum height of the reinforced soil structure was 26.80 m, with a total stretch length of 65 m. Additionally, Reno Mattresses were provided at the slope toe to protect against erosion.

Download
the Success Story

SOIL RETENTION MEASURES FOR TECHNO PARK PROJECT- TRIVANDRUM

Download
SOIL RETENTION MEASURES FOR TECHNO PARK PROJECT- TRIVANDRUM

Our products for
this Success Story

Get in touch with us

If you agree with the company's Privacy Policy and understood its content, the Data Controller asks you if you consent to the processing in manner provided in the company's privacy policy for sending promotional communications of the services / activities provided by the Data Controller. *

Furthermore, the Data Controller asks you if you give your consent for the communication of your personal data to the Maccaferri Affiliates, and the consequent extra-EU transfer that may result, for their own purposes, including of a promotional nature (sending marketing communications) *