RINGFIETSPAD ANTWERP

Yıl
2019
Konum
ANTWERP - ANTWERP - Belgium
Müşteri
Texion Geosythetics N.V.
Tasarımcı
Tractebel Engineering N.V.

Zorluk

This project has implied reinforced soil wall design, material supply and installation for a high-speed bike lane between the neighborhood of Deurne and Borgerhout in the city of Antwerp (Belgium). The main contractor was the Colas Group. Tractebel Engineering N.V. made the whole design with several different inclinations of the RSS to give a more natural and pleasant view. The walls were built along a very trafficked highway and they were aimed to act as a sound barrier for the houses in the suburban neighborhood as well. 

Çözüm

Mainly, four different types of facing inclinations have been used for this project: 27°, 34°, 45° and 60° The main product used is Terramesh Green Light that was produced specifically to meet the design requirements and slope inclinations. The project included also welded gabions walls and RSS built using EPS blocks to reduce the weight of the walls since the poor bearing capacity of the soil in situ. The construction took place between May 2019 and November 2019. In May 2020 the slopes were already completely vegetated.

İndirin: Başarı Hikayesi

RINGFIETSPAD ANTWERP

İndir
RINGFIETSPAD ANTWERP

Bu başarı hikayesiyle ilgili
ürünlerimiz Başarı Hikayesi

Bizimle iletişime geçin

Şirketin Gizlilik Politikası'na katılıyor ve içeriğini anladıysanız, Veri Sorumlusu, şirket tarafından sunulan hizmetler/faaliyetler hakkında tanıtım amaçlı iletişim gönderilmesi amacıyla, şirketin gizlilik politikasında belirtilen şekilde verilerinizin işlenmesine onay verip vermediğinizi sormaktadır. *

Ayrıca, Veri Sorumlusu, kişisel verilerinizin Maccaferri İştiraklerine iletilmesine ve bunun sonucunda ortaya çıkabilecek AB dışına aktarıma, kendi amaçları doğrultusunda, tanıtım amaçlı iletişim gönderimi de dahil olmak üzere onay verip vermediğinizi sormaktadır *