Desafío

The development was constructed in 2004 and included a basement level. Its retaining structures were built without the consideration of a vertical drainage system, which, after a few years, allowed water infiltration into the basement through the retaining walls.

Solución

The solution for this project involved the demolition of the existing retaining wall and the installation of a vertical drainage system using the Macdrain FP 2L drainage geocomposite. Macdrain was attached to the piles using a pin driver, with the non-woven geotextile side in contact with the soil. The collected water was directed to an underground drainage trench with a 0.5% slope and then routed to a sump pit also located underground.

Descarga
el Caso de Éxito

HELBOR BROOKLIN

Descargar
HELBOR BROOKLIN

Nuestros productos para
esta Caso de Éxito

Ponte en contacto con nosotros

Si está de acuerdo con la Política de Privacidad de la empresa y ha comprendido su contenido, el Responsable del tratamiento le pregunta si consiente el tratamiento de sus datos, en la forma prevista en la política de privacidad de la empresa, para el envío de comunicaciones promocionales sobre los servicios/actividades ofrecidos por el Responsable del tratamiento. *

Además, el Responsable del tratamiento le pregunta si consiente la comunicación de sus datos personales a las Afiliadas de Maccaferri, y la consiguiente transferencia extracomunitaria que de ello pueda derivarse, para fines propios de estas últimas, incluidos los de carácter promocional (envío de comunicaciones de marketing) *